Project Notifications & Updates

Find the latest information on ongoing and upcoming infrastructure projects that may impact water services, sewer systems, and streets within our community. Our goal is to keep residents and businesses informed with timely updates, schedules, and notices to help you plan ahead and stay connected. We appreciate your patience and cooperation as we work to improve and maintain essential public services.


2025

Fire Hydrant and Valve Replacements | 09.08.25-10.03.25 

Project Updates

September 24th, 2025

Work has commnced on the North side of Lodgepole Circle.  Crews will be installing new valves and a new hydrant.  This project is scheduled for two days with completion being set for 9/25.  Water outages can be expected over the course of the project during the day, but it is the goal to have service restored by 7pm each night.

September 23rd, 2025

The fire hydrant and valve replacement on North Side Circle is completed.  Crews have begun mobilizing equipement to the next project.

September 19th, 2025

The work on Sauterne has been completed, and water has been restored. On Monday, crews will begin work on North Side Circle. Please check your emails and messages for notifications on water outages. 

September 11th, 2025

Please see the updated timeline under "Anticipated Timeline" below. 

September 10th, 2025

We anticipate that the construction at the intersection of Ryan Gulch Ct and Ryan Gulch Rd will continue into Thursday, September 11th. This may impact the anticipated timeline below; updates will be provided as we have a better estimate. 

September 9th, 2025

Construction work has concluded on Fawn Court, and water has been fully restored. In the coming weeks, there may be some additional work in the area around this construction site, but it will have minor impacts on the street and residents. 


Summary

The district is actively working to improve emergency response and maintenance efficiency by replacing old or defective fire hydrants and faulty water isolation valves. This year, we aim to upgrade multiple hydrants to enhance accessibility and ensure reliable operation during emergencies. Additionally, due to a recent surge in water line breaks, we are prioritizing the replacement of more isolation valves than usual to help minimize service disruptions during both planned maintenance and emergencies.


Anticipated Timeline

The table below outlines the anticipated timeline of construction that will be taking place. This work may result in road closures and water outages in the areas listed. Water outages may be intermittent between 9 AM and 7 PM while work is being done and are not planned for any weekends. When water is restored, you may need to run your water for a few minutes until your water runs clear to remove any air trapped in the line. Changes to this timeline are likely, but the website will be updated as the district has updates available, and notifications will be sent to residents (who are registered in AquaHawk) affected by water outages the day before they take place, whenever possible. 

DatesRelative Location of Construction (In Roadway)Relative Location of Water Outage
Monday, September 8th100 Fawn CtRoads: Fawn Ct & Wildernest Rd.
Tuesday, September 9th100 Fawn CtRoads: Fawn Ct &  Wildernest Rd.
Wednesday, September 10th to Thursday, September 11thSilver Queen EastHOAs: Trailhead and Silver Queen East. Roads: Wildernest Rd.
Thursday, September 11th to Friday, September 12th Upper Salt Lick CircleHOAs: Salt Lick, Laredo Lofts, Summit Forest, Buffalo Mountain Townhomes, Retreat, Deck Gore, Aspen Glen, Bakkers Down Under, Sundance, Snowbird, Silverheels, and Eagles Nest Townhomes. Roads: Salt Lick Cir, Salt Lick Ct, and Silverheels Dr.
Monday, September 15th to Tuesday, September 16thLower Salt Lick Circle HOAs: Retreat, Deck Gore, Sundance, Aspen Glen, Bakkers Down Under, and  Buffalo Mountain Townhomes.
Wednesday, September 17thIntersection of North Side Circle and Sauterne LaneRoads: Parts of Sauterne Ln, North Side Cir, and Ryan Gulch Rd.
Thursday, September 18th to Friday, September 19thVillamont HOAs: Villamont and Woodworks. Roads: Lacy Dr, Burgundy Cir, and parts of Poplar Cir.
Friday, September 19th and Monday, September 22ndUpper Sauterne LaneRoads: Sauterne Ln, and parts of North Side Cir, and Ryan Gulch Rd.
Monday, September 22nd to Tuesday, September 23rdNorth Section of North Side CircleHOAs: Cortina Ridge, Buffalo Woods, Running Bear, and Village at Wildernest. Roads: Sauterne Ln, North Side Cir, and part of Buffalo Dr.
Wednesday, September 24th to Thursday, September 25th North Side of Lodge Pole CircleHOAs: Part of Treehouse. Roads: Parts of Lodge Pole Circle and Cutty Sark Ct
Friday, September 26thCul-de-sac End of Cutty Sark CourtRoads: Parts of Cutty Sark Ct.
Monday, September 29th to Tuesday, September 30th Middle of Cutty Sark Court Roads: Cutty Sark Ct and parts of Buffalo Dr.
Wednesday, October 1stEagle's Nest CourtRoads: Eagle's Nest Ct.
Thursday, October 2nd to Friday, October 3rdBuffalo Drive, just North of Silverheels DriveHOAs: Cortina Ridge, Buffalo Woods, Running Bear, and Village at Wildernest. Roads: Part of Buffalo Dr. 

 