Skip to main content

Project Notifications & Updates

Find the latest information on ongoing and upcoming infrastructure projects that may impact water services, sewer systems, and streets within our community. Our goal is to keep residents and businesses informed with timely updates, schedules, and notices to help you plan ahead and stay connected. We appreciate your patience and cooperation as we work to improve and maintain essential public services.

Want notifications via email or text? Sign up for AquaHawk

Old Water Tank 2 Abandonment | 05.2026-07.2026 

LOCATION: POPLAR CIRCLE


UPDATES

4-20-2026

The District has begun removing the old water tank and pump house located on Poplar Circle.
The site has been secured with fencing, and topsoil has been stripped in preparation for demolition. Empire Demolition is currently dismantling the existing metal water tank. The removed metal components are being staged on-site until full truckloads can be transported for recycling.
This tank has been out of service since the new water tank was constructed on Ryan Gulch Road and is no longer needed.
Following removal of the tank, crews will demolish the underground concrete vault and pump infrastructure. Demolition activities are expected to be completed by mid-May.
Residents may notice increased noise and some truck traffic in the area during this time; however, no road closures or detours are anticipated.
Once demolition is complete, Buffalo Mountain Metro District will begin backfilling and restoring the site throughout the summer. There are currently no plans for future development of the site.
For safety, residents are asked to stay clear of the fenced construction area while work is ongoing.


SUMMARY

The district replaced this water storage reservoirs in 2020 to increase the size and pumping capacity of the water tank to help with demand and control of the water system. This project is to remove the old water tank and to restore the site to be utilized for storage or other district needs in the future.


ANTICIPATED TIMELINE

This project is scheduled to take place from May to July of 2026. A more detailed timeline will be provided when available. 

Ryan Gulch Water Main Replacement | 06.15.2026-09.2026 

LOCATION: RYAN GULCH RD BETWEEN CUTTY SARK CT AND UPPER LODGE POLE CIR


UPDATES

Construction on the water main between Cutty Sark and Upper Lodge Pole Circle will begin on Monday, June 15th 2026. Water shut down will occur on Tuesday, June 16th, 2026. Affected residents will be notified via Aquahawk notification system. Please make sure you are registered for alerts.  


SUMMARY

This section of the water main has been identified as a problem area, where main breaks more commonly occur, and because of that, it is the first section scheduled to be replaced. 


ANTICIPATED TIMELINE

This project is scheduled to take place from June,15 of 2026 to September of 2026. A more detailed timeline will be provided when available. 

Ryan Gulch Road Storm Sewer | 06.2026-09.2026 

LOCATION: RYAN GULCH RD BETWEEN UPPER & LOWER POPLAR CIR


UPDATES

Once the project is underway, updates will be posted here as available. 


SUMMARY

Ryan Gulch Road Storm Sewer Update

Storm Sewer | 06.2026-09.2026

LOCATION: RYAN GULCH RD BETWEEN UPPER & LOWER POPLAR CIR

UPDATES

Once the project is underway, updates will be posted here as available.

SUMMARY

June 2026

Dear Residents,

Buffalo Mountain Metro District’s contractor, CHM Concrete, has received final permit approval from Summit County and anticipates beginning construction on or around June 15, 2026 weather dependent.

This project will replace the existing roadside ditch with a storm sewer system and replace driveway culverts along the corridor. The goal is to remove a deep and potentially hazardous ditch, improve drainage, assist with winter snow plowing operations, and support the continued development of a future bike path.

Construction is anticipated to begin in early June. Work is expected to take approximately six weeks, with an additional week for bike path paving.

Work hours will generally run from 7:00 AM to 6:00 PM Monday through Friday, with the potential to operate between 7:00 AM to 7:00 PM Monday through Saturday if needed, in accordance with local regulations.

During construction, downhill traffic on Ryan Gulch Road will be closed, and a detour will be in place via Poplar Circle. Residents should expect temporary impacts within the construction area, including periodic driveway access impacts, traffic delays, construction noise, and increased truck traffic.

The pedestrian path and downhill bike lane will be closed for the duration of construction and used for staging as well as limited resident access.

We also want to emphasize safety during this project. Construction zones can present hazards, and we ask that residents help by ensuring children and pets are kept a safe distance from active work areas.

We recognize that projects like this can disrupt daily routines, and we truly appreciate your understanding. The District and our contractor, CHM Concrete, are committed to minimizing these impacts and completing the work as efficiently as possible while maintaining safety and quality.

Project updates will be shared regularly through the District website as well as other forms of communication for homes being directly impacted.

Thank you for your patience and cooperation. If you have any questions, please feel free to contact me directly.

Sincerely,

Calvin Stewart – Project Manager

Buffalo Mountain Metro District – Streets Department

Calvin@bmmd.org


ANTICIPATED TIMELINE

This project is scheduled to take place from late May/ early June to September of 2026. A more detailed timeline will be provided when available. 

PRV Zone 6/5 | 06.2026-07.2026 

LOCATION: INTERSECTION OF RYAN GULCH RD & BASHORE CT


UPDATES

Once the project is underway, updates will be posted here as available. 


SUMMARY

The District has been installing control valves that connect our 5 water pressure zones. These valves open in times of large fire flow events to increase the water storage capacity for firefighters. This project will be the third PRV to be installed in the District.


ANTICIPATED TIMELINE

This project is scheduled to take place from June to July of 2026. A more detailed timeline will be provided when available. 

Town of Silverthorne Interconnect | 07.2026-08.2026 

LOCATION: BMMD WATER PLANT - ADAMS AVE


UPDATES

Once the project is underway, updates will be posted here as available. 


SUMMARY

The District is working with the Town of Silverthorne to connect our drinking water systems. The interconnect can be used in times of emergencies, such as water main breaks, issues in the water plant, or with our wells, and will also be used for scheduled maintenance to our water plant. 


ANTICIPATED TIMELINE

This project is scheduled to take place from July to August of 2026. A more detailed timeline will be provided when available. 

Join our mailing list